Rehab Scope of Work and Draw Schedule: How to Build One a Lender Will Fund

A fundable rehab scope lists every item by trade, with a quantity, a unit and a price, so anyone can check what was bought. The draw schedule then groups those lines into stages that each end at something an inspector can see finished, which is what keeps money moving on a flip or BRRRR.

Last updated:

Rehab budgets go wrong in two predictable ways. The scope is too vague to price honestly, so the real cost only appears once walls are open; or the payment stages are tied to the calendar instead of finished work, so cash runs out halfway. Both are fixed on paper before the first swing of a hammer. This guide gives the structure we use, without made-up numbers: your prices depend on the house, the market and the finish level, and your lender sets its own draw rules.

Part 1: the scope, written by trade

Organize the scope in the order the work actually happens. Every line gets five things: a location, a description specific enough to verify, a quantity, a unit, and a price. Here is how the sections and a few sample lines look.

SectionExample lines (described, not priced)
1. Site, permits, protectionPermit and plan fees for the city or county; dumpster pulls (each); floor and fixture protection; lead-safe setup if the house predates 1978
2. DemolitionRemove kitchen cabinets and tops; remove carpet and pad (sq ft); remove damaged drywall (sq ft, by room)
3. Structure and envelopeReplace rotten subfloor (sq ft allowance); sister or replace framing (lin ft); repair fascia and soffit (lin ft); roof repair or replacement (squares)
4. Systems rough-inElectrical panel and circuits by a licensed electrician; supply and drain lines by a licensed plumber; HVAC equipment and ducts
5. Insulation and drywallInsulation (sq ft); hang, finish and texture drywall (sheets or sq ft)
6. FinishesCabinets (lin ft) and tops (sq ft); flooring by type (sq ft); interior doors (each); trim (lin ft); paint (rooms or sq ft)
7. Fixtures and finalPlumbing fixtures (each); light fixtures (each); appliances (each); hardware; final clean
8. Exterior and sitePressure wash; exterior paint; concrete repair (sq ft); landscaping and grading

Allowances and unit prices for what you cannot see

Some costs cannot be known until demolition. Name them in the scope with a unit price instead of leaving them out: subfloor per square foot, sill plate per linear foot, framing repair after a termite treatment, a sewer-line repair after a camera inspection. A surprise then becomes a priced change order, not an argument.

Alabama items that belong in most scopes

  • Pre-1978 houses. EPA's Renovation, Repair and Painting rule requires anyone paid to disturb paint in housing built before 1978 to be certified, including small firms. Give lead-safe setup and cleanup their own line so they are not cut when the budget gets tight.
  • Termite damage. Common in older Alabama houses. Treatment comes from a licensed pest control company first; the framing repair follows as its own line.
  • Crawlspace moisture. Humid summers soak crawlspaces. Vapor barrier, drainage at the downspouts and grading usually belong in the scope before new flooring goes down.
  • Clay soil and concrete. Settled walks and driveways on expansive clay are common; see the concrete on clay soils guide before pricing flatwork.
  • Coastal houses. In Gulf Shores, Orange Beach and the rest of Baldwin County, budget for salt-air wear on exterior metal, and check flood-zone rules with the building department before a large renovation.

Part 2: the draw schedule, tied to visible milestones

A good draw ends at a point an inspector can confirm by looking. Group the scope sections above into stages like these, and write the finished condition for each stage in plain words.

  1. Mobilization and demolition complete: debris gone, permits posted, the house down to what stays.
  2. Structure and dry-in complete: framing and subfloor repaired, roof and openings watertight.
  3. Rough-ins passed: electrical, plumbing and mechanical rough inspections signed off where permits require them.
  4. Drywall complete: insulation in, drywall hung and finished, ready for paint.
  5. Finishes installed: cabinets, tops, flooring, doors and trim set.
  6. Final: fixtures, paint, punch list, final inspections and clean.

Each line of the scope belongs to exactly one stage, so the stage totals add up to the scope total. When the lender's inspector arrives, the stage description and the photos from that stage are what they check against.

Change orders

Every change, up or down, goes in writing before the work: what changed, the price from the agreed unit rate, and which draw stage it lands in. Keeping change orders tied to stages means the draw schedule stays true to the money, which is the whole point of having one.

Review the scope before it goes to the lender

Read it once as the inspector will. Every line should point to a place in the house and a quantity someone could count, and every stage should end at work that can be photographed finished. Lines that fail either test are the ones that cause disputes later.

Before you commit to a purchase price

Price the scope first, then decide what you can pay. The free Deal Analyzer takes the rehab total and works back to a maximum offer, profit and return, so the scope and the offer are built from the same number.

Source

  • U.S. Environmental Protection Agency, “Lead Renovation, Repair and Painting Program,” epa.gov (page updated June 17, 2026; read October 16, 2026).

Frequently asked questions

What is a draw schedule?

A plan that splits the rehab budget into stages, each paid when a defined piece of work is finished. If your lender holds back rehab funds, the draw schedule is what its inspector checks the work against before releasing money.

How many draws should a flip have?

There is no single right number, and your lender may set it. What matters is that each draw ends at work an inspector can see and verify, such as framing complete or cabinets set, not a vague percentage of the whole job.

Why line items instead of one number per room?

Because a lender, a partner or a buyer’s appraiser can check a line item. A line that reads replace 14 interior doors with slab, hardware and casing can be priced, verified and compared. A line that reads kitchen cannot.

How should a scope handle surprises behind walls?

Name the likely ones in advance as allowances or unit prices: subfloor per square foot, rotten sill per linear foot, termite-damaged framing repair after treatment. When one shows up, it is priced from the agreed rate, approved in writing and added as a change order.

Will you build the scope for a property I am about to buy?

Yes. Walk it with us before closing or during due diligence and we will write the scope in the line-item and draw structure on this page, ready for your lender.

Get a scope written before you close

Send the address and your due-diligence date. We will walk it and write the line-item scope and draw plan.